Pump Station #22

Overview

The Miami-Dade County Department of Regulatory and Economic Resources through its Environmental Resources Management (DERM) in July 2023 imposed a consent decree moratorium on seven of the City's sanitary sewer (wastewater) basins due to inflow/infiltration flows exceeding the established maximum levels. However, the City's Public Works Department has been working diligently to address and fix the identified issues in Pump Station #22. 

To date, the City has successfully repaired two of the affected basins, specifically those associated with Pump Stations 15 and 46. One of these basins has been granted full approval from DERM, while the second has transitioned from a temporary moratorium to a conditional status, indicating it is in a trial period to ensure it is fully fixed.

In a significant move to expedite the necessary repairs to the remaining five basins, the administration plans to have the City Council approve a contract with a specialized sewer pipelining company. 

Timeline

The goal is to accelerate the repair process, with all work projected to be completed by December 2024. 

Project Construction Cost

$5,141,905

Project Number

CIP#2355 A & B 

District

This project is located in District 4